Skip to main content

Final oversight report on Data Center relocation project

Final oversight report on Data Center relocation project

May 18, 2011

The county successfully opened its new data center in November 2009. The Data Center Relocation Project was undertaken due to concerns about the adequacy of the electrical, HVAC and fire suppression systems, and server capacity at the county’s main data center in the Seattle Municipal Tower Building (SMT). The county also needed to vacate SMT because as of March 2007, the data center was in a month-to-month lease. All work on the project was completed in September 2010.

The county relocated its data center to a facility built to its specifications at the Sabey Data Center in Tukwila. The new facility opened on schedule, but milestone delays occurred. Completion was on budget, but secondary fiber and decommissioning costs at SMT significantly more than estimated. This required spending 75 percent of contingency. The total budget for the project was $20.3 million; the actual cost of the project was approximately $19.3 million.

Appropriate operating procedures for the new facility are in place. Most user agencies report satisfaction with the new location. The new data center is capable of eventually housing all of the county’s network servers. This project relocated about half of them. The executive is working on a new project to relocate additional servers to the site in response to council provisos included in the 2011 budget.

Watch the presentation

The Auditor has followed up on the report to evaluate implementation of our recommendations. See the most updated information below.

 

Prior reports on this project are found below.

          Download the report


Of the 2 recommendations:
DONE 1 Recommendation has been fully implemented. Auditor will no longer monitor.
PROGRESS 0 Recommendations are in progress or partially implemented. Auditor will continue to monitor.
OPEN 0 Recommendations remain unresolved. Auditor will continue to monitor.
CLOSED 1 Recommendation is no longer applicable. Auditor will no longer monitor.

Final project summary

This report provides a final assessment of the Data Center Relocation Project (Data Center or project), which relocated King County’s primary data center from leased space in the Seattle Municipal Tower (SMT) to leased space in the Sabey Data Center in Tukwila. The project was completed in September 2010. In addition to assessing the final scope, schedule, and budget results, this report summarizes project lessons learned based on feedback from major stakeholders, the project team, and data center customers.

The Metropolitan King County Council (council) added independent oversight of the Data Center Project to the King County Auditor’s Office (KCAO) work program in September 2008. We provided 11 project status reports to council between December 2008 and April 2010 and briefed the Government Accountability and Oversight Committee on two occasions. This report closes out KCAO’s oversight effort.

The project team successfully delivered the final scope but the lease acquisition process could be improved. See the full report for more details.

The new data center opened on schedule, but delays occurred in three major project elements one of which increased project costs. See the full report for more details.

The project was delivered within budget but several project elements cost significantly more than estimated. See the full report for more details.

Read the full report for risk details.

The executive should establish policies to ensure consistent budgeting and reporting of the staff labor costs on capital projects, including costs for staff funded by agency operating budgets.

The executive should evaluate the adequacy of its policies and procedures for authorizing lease acquisitions and amendments.

Reports related to this audit

Click on the image(s) below to view the follow-up reports.

September 14, 2015
Download the report


The oversight reports provide a review of the status of scope, schedule, budget, and risk for the Data Center Relocation project. The reports are found below in chronological order starting with 2011.

Data Center reports for 2011

Final oversight report on Data Center relocation project, May 18, 2011

 

Data Center reports for 2010

Data Center relocation project oversight report for December 2009 through March 2010, April 22, 2010

 

Data Center reports for 2009

Data Center relocation monthly oversight report, April 20, 2009

Data Center relocation project oversight report for February 2009, May 14, 2009

Data Center relocation project oversight report for March 2009, June 4, 2009

Data Center relocation project oversight report for April 2009, July 2, 2009

Data Center relocation project oversight report for May 2009, July 24, 2009

Data Center relocation project oversight report for June 2009, September 9, 2009

Data Center relocation project oversight report for July through November 2009, January 15, 2010

 

Data Center reports for 2008

Data Center relocation monthly oversight, December 23, 2008

Data Center relocation monthly oversight, January 16, 2009

Data Center relocation monthly oversight, March 5, 2009

Currently, there are no related reports to this project.

 

Audit team

Tom Wood and Tina Rogers conducted this work. If you have any questions or would like more information, please call the King County Auditor's Office at 206-477-1033 or contact us by email KCAO@kingcounty.gov.

expand_less