Special study of FMD's management of project delivery

Special study of FMD's management of project delivery

November 17, 2011

NEW! Download the latest follow-up report

This study provides a high-level review of the Facility Management Division's (FMD) capital project delivery on maintenance, rehabilitation, and parks projects. We found opportunities for improvement of its management practices. Overall, FMD's processes for developing initial project scope, schedule, and budget, lack rigor and compounded by the constraints of the county's budget development timelines, result in unrealistic or incomplete budget requests. FMD's former planning tools may result in over scheduling of project managers and some work processes are not consistently followed. Moreover, FMD lacks meaningful performance measures to adequately assess program results. Monitoring of project progress has often been conducted in an ad hoc manner without tracking project results to baseline plans.

Status

Of the 5 recommendations:

DONE 5 Recommendations have been fully implemented. Auditor will no longer monitor.
PROGRESS 0 Recommendations are in progress or partially implemented. Auditor will continue to monitor.
OPEN 0 Recommendations remain unresolved. Auditor will continue to monitor.
CLOSED 0 Recommendation is no longer applicable. Auditor will no longer monitor.

Summary

In 2011, FMD was managing 141 active projects totaling more than $88 million. These projects include parks capital projects and facilities rehabilitation and care of county facilities. Effective delivery of projects results in benefits to county residents and efficient expenditure of county resources.

We found that FMD's development of initial project scope, schedule, and cost estimates lack rigor resulting in unrealistic or incomplete budget requests. We also found that workload planning methods may over-schedule project managers. As a result, projects planned for completion in the calendar year often carry over and require resources in the next year or beyond. FMD does very limited monitoring of budget versus actual project costs. Finally, FMD lacks meaningful performance measures for effective management of project delivery.

We make three recommendations to facilitate a more robust accountability framework for capital project delivery. First, ensure a more rigorous planning process focusing on establishing baseline scope, schedule, and budget. Second, establish meaningful performance measures. Third, develop and apply standards to ensure that estimates are consistent with best practice for appropriation requests.

Reports related to this audit

Click on the image(s) below to download the follow-up reports.

April 1, 2019
Download the report

December 22, 2017
Download the report

December 13, 2016
Download the report

January 25, 2016
Download the report

Click on the image(s) below to view related reports.

September 16, 2014
Download the report
More info about this report

  

December 21, 2011
Download the report
  

  

February 12, 2008
Download the report
 


Audit team

Tina Rogers and Brian Estes conducted this audit. If you have any questions or would like more information, please call the King County Auditor's Office at 206-477-1033 or contact us by email KCAO@kingcounty.gov.

expand_less