Project description

The County has completed repairs and replacement of a 2-mile pipeline that has been serving the Bothell area since 1970. The new pipeline will increase system reliability and capacity to accommodate population and business growth in this portion of the service area.

Since early 2018 the new pipe has been carrying wastewater flows and providing increased system capacity and reliability. The new pipe was installed using both trenchless and open cut construction methods.

The map, below, shows the different work areas and construction methods for the project.

Vicinity map for North Creek Interceptor Project 

Schedule

King County began work on this project in early 2015. Installation of the new pipeline was completed in early 2018. Final street paving in the Canyon Park Business Center was done this summer and final striping is scheduled to be completed by the end of the year. These areas will be monitored through 2023 to ensure the restoration was successful. 

Project library

24-hour emergency and odor reporting:

Contact West Point Treatment Plant at  206-263-3801.

Visit Software Help if you have trouble viewing or downloading documents.

Thursday, February 28, 2013
6:30 – 8 p.m., presentation at 7:00 p.m.
Crystal Springs Elementary School Library,
21615 9th Ave. SE, Bothell

Community meeting. Learn about the North Creek Interceptor Project and ongoing maintenance and repair activities in the Bothell area. 

DNS and Environmental Checklist (PDF file, 4.5MB), issued May 24, 2013