Vashon Highway SW paving extents
Map showing the stretch of Vashon Highway SW that will be paved this summer. Larger map PDF

Latest update: June 18, 2018

Pavement grinder
Grinding work on Vashon Highway SW.

Grinding work on Vashon Highway SW began today (June 18, 2018) at SW Bank Road. The grinding and paving work within the main business district is expected to take five days and requires a lane closure from 7 a.m. to 5 p.m. Please check back for updates.

On this page

Contact us

Brent Champaco, Community Relations Planner
Desk 206-477-9094
Cell 206-573-4267
Email

Stay connected

Sign up for alerts

Follow us!

Look at Twitter

Update: June 13, 2018
Paving and grinding work on Vashon Highway SW is scheduled to begin Monday, June 18 on SW Bank Road and continue south through the main business area. The work within the main business district is expected to take five days and requires a lane closure from 7 a.m. to 5 p.m. Motorists should expect delays. Please consider using alternative routes. Click HERE (PDF) for more details. Click HERE to see the map.

Once the grinding and paving work in the business district is complete, the contractor plans to continue working south toward the Tahlequah Ferry Terminal and then move back north to pave the portion of the highway near the Vashon Ferry Terminal to Fauntleroy/Southworth. This work is anticipated to begin Monday, June 25 and entails daytime grinding work and nighttime paving. The nighttime work hours are anticipated to be 7 p.m. to 5 a.m. During this work, residents along the work zone may hear construction noise associated with the paving. The daytime grinding work is expected to occur from 7 a.m. to 5 p.m. During the daytime and nighttime work, the road will be reduced to one lane with flaggers and/or a pilot car directing traffic. Parking within the work zone will be limited. Please see dates and times posted on the no parking signs. Click HERE (PDF) for more details.

Update: May 31, 2018
Four drainage and pavement repair projects are scheduled to take place along Vashon Highway SW in June. This is preparation work for the upcoming paving project on Vashon Highway SW which is anticipated to begin in mid-June. Upcoming drainage and pavement repair projects:

  • Vashon Highway SW at house #23621. One travel lane will be closed 24-hours a day, Tuesday, June 5 at 8 a.m. to Friday, June 8 at 3 p.m. Map
  • Vashon Highway SW at house #24115. Daytime lane closure from 8 a.m. to 3 p.m., Tuesday, June 5 to Friday, June 8. Map
  • Vashon Highway SW between house #24150 and #24131. Daytime lane closure from 8 a.m. to 3 p.m., Monday, June 11 at 8 a.m. to Friday, June 22 at 3 p.m. Map
  • Vashon Highway SW at Dugway Road SW. Daytime lane closure from 8 a.m. to 3 p.m., Thursday, June 13 at 10 a.m. to Thursday, June 21. Map

Update: May 22, 2018
The drainage repair work on SW 178th Street, between Vashon Highway SW and 99th Place SW, has been extended to Friday, June 1. The work requires a daily, full closure from 9 a.m. to 2 p.m. Map

Update: May 7, 2018
Drainage repair work will take place on SW 178th Street between Vashon Highway SW and 99th Place SW from Thursday, May 17 through Friday, May 25. The work requires a daily, full closure from 9 a.m. to 2 p.m. A detour will be posted. Map

Update: April 26, 2018
Some pre-pavement work will start as early as May, when old drainage infrastructure will be replaced and other necessary roadway repairs will be made before the repaving begins. The first of the road repair work is scheduled to begin Monday, May 14 at 8 a.m. on Vashon Highway Southwest from Southwest Pohl Road to 1000 feet north near the Tahlequah ferry dock. The work requires a 24-hour lane closure through Monday, May 21. Detour signs will be posted for ferry traffic. Motorists should expect delays. It is anticipated that the actual repaving will begin in June, depending upon weather and the contractor’s schedule. Map | Blog article

Project overview

Paving will take place on 12 miles of Vashon Highway SW in 2018. The work is anticipated to begin early this summer. This webpage will provide updates on the paving project and photos of the progress. Please check back regularly and consider signing up for Road Alert emails and text messages.

Frequently-asked questions

How much of Vashon Highway will be paved this year?
Paving will take place on 12 miles of Vashon Highway in 2018. Two portions of the roadway that were paved in 2009 will not be included in the project. The sections from SW Bank Road to SW 156th Street and from just north of SW 140th Street to SW 132nd Place will not be paved as part of this project.

How long will the project take?
The contract allows approximately three months for the contractor to complete all of the work in the contract. The work is weather dependent.

How long has it been since the 12 miles have been paved?
It’s been about 25 years since a 12 mile stretch of the highway has been repaved.

Why pave the road?
The majority of the highway is in poor condition with various types of pavement defects (alligator cracking, potholes, raveling, longitudinal cracking, etc.) visible throughout the project limits. If delayed to the point where more significant repairs or full reconstruction is needed, costs would be three to five times as much depending on the amount of damage to the subgrade.

When will the Vashon Highway paving project begin?
The work is anticipated to begin early this summer. King County is in the process of hiring a contractor for this project. Once this process is complete, the schedule will be determined and we will send out an update with the schedule for the work. Updates regarding anticipated work start dates and activities will be posted on the Vashon Highway Paving Program webpage and a Road Alert email/text will be sent. To sign-up for Road Alert emails/text messages, click the red button to the left under Stay Connected.

Will paving work be done during the Strawberry Festival or the 4th of July?
No. Paving work will not be conducted from Thursday, July 19 through Sunday, July 22. Work will also not take place on Tuesday, July 3 or Wednesday, July 4.

Will this work require lane restrictions and detours?
The project will require a lane closure while crews conduct the paving work. Detours will be put in place or one lane with flaggers will move traffic through the work zone.

Any changes to rumble strips on Vashon Highway?
King County data shows that the rumble strips on Vashon Highway have led to a 30-percent reduction in crashes since their original installation about five years ago. This is a significant improvement in road safety for the people of Vashon Island and makes the reinstallation of rumble strips on Vashon Highway after the paving project is complete – in the same place and pattern as they are today – a matter of public safety.

National studies by the Federal Highway Administration show that the installation of rumble strips leads to an average reduction in crashes of nearly one-third. In King County, we have seen similar results. In South King County, for example, centerline and shoulder rumble strips on Petrovitsky Road east of 151st Ave SE have shown a 42-percent reduction in crashes after five years, and centerline and shoulder rumble strips on SE 400th Street from SR 164 to SR 169 have shown a 32-percent reduction in crashes.

Residents have asked whether we can instead add bike lanes to Vashon Highway. There are two issues with this. First, the public right-of-way on Vashon Highway is of a limited width, so adding bike lanes would likely require property acquisitions from most individual property owners for the length of any new bike facilities. Additionally, the limited funding available for county roads is currently spent on primarily critical safety issues and preservation of existing roads and facilities. There are not funds available for new facilities, like bike lanes that require property acquisition, or other capacity and mobility projects. Acquiring property and funding for a project of this significance is not feasible given existing resources. We are happy to hear from cyclists about specific location issues and will evaluate specific areas to determine whether or not modifications might be warranted.

Photos

Vashon Highway pavement damage
Damaged roadway on Vashon Highway SW.
Larger photo JPG
Vashon Highway pavement damage
Another view of the roadway damage on Vashon Highway SW.
Larger photo JPG
Vashon Highway SW & SW Burton Drive
Intersection of Vashon Highway SW & SW Burton Drive.
Larger photo JPG