A feedback survey will be open to the public from November 2 to 20, 2026 to help the County learn more about the factors the community values in making this decision. 

Flooding around the Snoqualmie river

Flooding around the Snoqualmie river after heavy rains on Oct. 22, 2019, on NE Tolt Hill Road. Photo: King5

Overview

This study looks at different ways to reduce or eliminate traffic problems caused by flooding in the Snoqualmie Valley. It focuses on keeping one of four existing roads and bridges that cross the Snoqualmie River open during floods rather than solving the flooding itself. The County and our partners began the Cross Valley Study in December 2022. 

The first phase of the feasibility study was completed in October of 2024 and identified two routes (see map below) for further review. Now the County is completing further review to select one of the two corridors. A public survey will be open to help the County learn more about the factors the community values in making this decision. This survey will be open to the public from November 2 to 20, 2026.

Share your Feedback
Survey open from November 2 to 20, 2026

The information gathered in this study will help inform efforts to secure construction resources. Without identified funding, we do not have an estimated start date for construction.

 

Community Feedback

The study team has identified two alternative routes for further review and is seeking feedback from the community to help the County learn more about the factors the community values in making this decision. Both NE Tolt Hill Road and NE 124th Street have emerged as roads that, if dedicated resources become available, could be improved to make it safer and quicker to recover when flooding occurs. This information is based on what we know today about both corridors, but our understanding may shift as we gather more data.

Please read below for benefits and challenges of each option:

NE Tolt Hill Road

If selected, NE Tolt Hill Road would be raised using a long bridge-like structure (a trestle) across the entire valley, from the existing Tolt Bridge to Fall City-Carnation Road NE (State Route 203). It is shorter than NE 124th Street and has fewer engineering problems to solve. It would improve road width and safety. But it has complicated permitting, land impacts, and the public right-of-way will need to be widened.

Rendering 1 of tolt bridge

NE Tolt Hill Road and bridge in current conditions looking east towards SR 203

Render 2 of NE Tolt Hill Road

A rendering of what NE Tolt Hill Road and Bridge looking east could look like if the road was raised using a trestle.

*Driveways are not shown in the images above.

Pros

  • The shorter length lowers costs and shortens construction time.
  • Fewer engineering problems compared to NE 124th Street (ex., soil is “fair,” not “poor”).
  • The existing Tolt Bridge – 1834A mostly stays as-is (it does not need to be raised).
  • Future nearby projects (like upgrades to SR 203 and flood reduction projects on the Tolt River) may further improve access during floods.
  • People in the southeast valley could reach this road during future severe floods compared to NE 124th Street.
  • Improves the currently narrow road section.
  • Good improvement for emergency access in the southeast valley.

Cons

  • Harder and slower to permit because of rules about farmland and parks.
  • Public right-of-way will need to be widened. This may affect some adjacent properties.
  • Nearly the whole project is inside a high-risk river migration zone, making foundation work challenging.
  • Would cause more road users to detour from their typical route during flood conditions because fewer people typically use this road.
  • Many underground utility lines and water lines will need to be moved. This work increases time and cost.

NE 124th Street

If selected, NE 124th Street would be raised using a long trestle structure similar to that considered for NE Tolt Hill Road, across the entire valley from W Snoqualmie Valley Road NE to Carnation-Duvall Road NE (State Route 203). NE 124th Street is longer and sits lower in the valley. It has very poor soil, and the Novelty Bridge #404B would need to be raised and retrofitted. It improves access for the northern part of the valley but has higher cost, complex engineering, and environmental impacts.

Render of NE 124th Street 1

NE 124th Street in current conditions looking west. 

Render of NE 124th v2

NE 124th Street if the road were to be raised using a long trestle structure. 

*Driveways are not shown in the images above.

Pros

  • Less traffic congestion during floods.
  • Fewer impacts with adjacent properties.
  • Utilities are mostly overhead and easier to move.
  • Smaller impacts from river channel migration area.
  • People in the northeast valley could reach this road during future severe floods compared to NE Tolt Hill Road.
  • Right-of-way width already meets county standards in many places.
  • Permitting is simpler compared to NE Tolt Hill Road.

Cons

  • The longer length and poor soil make the cost much higher, perhaps double or triple the cost. Higher cost because the corridor is longer and the soils are very poor which makes building the foundation harder.
  • The Novelty Bridge must be raised and its foundations retrofitted, which is very complex and costly work.
  • More wetlands may be affected by the project because the corridor is longer.
  • Longer construction time than NE Tolt Hill Road.

Side by side comparison

Please read below for a side-by-side comparison

 

Side by side comparison table

 

NE Tolt Hill Road

NE 124th Street

Overview

NE Tolt Hill Road is cheaper, shorter, and has fewer engineering issues, but harder to permit and affects more properties.

NE 124th Street works better for traffic and has fewer landownership problems, but costs much more, takes longer to build, and the soil makes it more difficult to construct.

Cost

  • High cost

  • Higher cost

Construction

  • Shorter construction time

  • Existing bridge mostly stays as-is

  • Soils are generally fair making foundation work standard

  • Longer construction time

  • Novelty Bridge must be raised and retrofitted

  • Very poor soils make foundation work tricky

Engineering challenges

  • Fewer engineering challenges

  • Deep drilled shafts may be challenging

  • The corridor is in a high-risk river migration zone, making foundation and river erosion work harder

  • Major engineering challenges

  • Deep river erosion, poor soils, and complicated bridge raising

  • Requires a complex foundation that is more difficult and costly to construct

Environmental impacts

  • Fewer wetland impacts

  • Limited impacts to aquatic areas

  • More wetland impacts

  • Some impacts to streams and Snoqualmie River

Access during floods

  • Flooding of roads accessing NE Tolt Hill Road happens more often right now than at NE 124th Street

  • Other King County planned flood reduction projects will improve access to this corridor

  • In the future, worse flooding will make NE 124th Street even harder to access during floods than NE Tolt Hill Road

Property & public land impacts

  • Public right-of-way will need to be widened. This will affect some adjacent properties

  • Impacts to land used for parks and agriculture have special rules and regulations that add a lot of time and cost

  • Smaller property impacts

  • Fewer property complications overall

 

Utilities

  • An existing water line and buried power/fiber are harder and more costly to move

  • Mostly overhead utilities, which are easier to move

 

 

Keeping key routes open

The four major roads and bridges that cross the valley and the Snoqualmie River are used by about 25,000 vehicles daily.

The study began by focusing on the four east-west roads and bridges over the Snoqualmie River between Duvall, WA and Carnation, WA. During floods, these four roads often close, cutting off important routes and isolating communities. From north to south:

  • NE Woodinville Duvall Road
  • NE 124th Street/Novelty Road 
  • NE Carnation Farm Road
  • NE Tolt Hill Road

Map graphic

In phase one of the study, the team studied the four routes and identified two roads (NE Tolt Hill Road and NE 124th Street) for further review during phase two to decide which one the County could improve when budget is available. 

Impact of Flooding

Floods happen almost every year. High water can damage homes and close roads, making it hard for people to get around. Farms are also affected, which can hurt farmers financially. In addition, floodwaters can also change the river’s shape and flow, leading to more environmental and infrastructure challenges.

Topics that were covered in the study 

The study explored 12 main topic areas to recommend ways to keep traffic moving in the Snoqualmie Valley. The goal was to use what we learned to develop practical solutions to manage traffic and reduce road disruptions during floods.

Design and Engineering

  • Bridges and Culverts: Looked at how to design and build bridges and culverts (structures that allow water to flow under roads) that can handle both traffic and strong water flows.  
  • Traffic: Studied how vehicles move through the area to design roads that reduce traffic jams, improve safety, and keep goods and people moving.
  • Construction Options: The team looked at how difficult each proposed option is to build and how much each option will cost. 

Environmental Considerations

  • Soil and Ground Stability: Experts checked the stability of soil, and water flow to make sure roads and bridges are built safely and can withstand and resist floods, slides, and earthquakes.
  • Water Flow (Hydrology and Hydraulics): Studied how water moves in rivers, streams and pipes. This helps us to design bridges and culverts that manage water well during floods.
  • Environmental Impact: Reviews how construction might affect nature, including plants, animals, and water quality. This helps make sure that roads and infrastructure are built in a way that minimizes impact to the environment and meets current regulations.

Land Use

  • Mapping and Surveying: Creates maps and measures land to guide where roads, bridges, and buildings should go.  
  • Land Use and Zoning: Understands how the land is used for different things, like homes, farms, businesses, and follows zoning laws to figure out where roads can go and how they affect local communities.

Community and Land Concerns

  • Cultural Resources: Ensures construction doesn’t damage historical sites, landmarks, and places that are important to Native American heritage.
  • Land Ownership (Real Property): Understands what impacts, if any, there will be to adjacent properties.
  • Community Outreach: Informs local residents and communities about upcoming projects and get their input. This helps make sure the community’s concerns and needs are considered.

Summary of Cross Valley Study (CVS) phase one decision making

The first phase of the Snoqualmie Valley Major Flood Mitigation Study examined the relative feasibility of potential flood improvements to NE Tolt Hill Road, NE Carnation Farm Road, NE 124th Street, and NE Woodinville-Duvall Road. It selected the following two roads for more data collection and a more detailed study:

  • NE Tolt Hill Road Key benefits of this corridor are:
    • it would reduce isolation of locations without access to medical services
    • it is relatively short, which would reduce the cost and complexity of construction
  • NE 124th Street Key benefits of this corridor are:
    • many people already travel on the route, so they wouldn’t have to change their route during flooding
    • the right-of-way is already wide, so an improvement would be less likely to affect adjacent properties

A high-level summary of the factors considered by the study, and the relative importance assigned to each factor, are shown in the table below.

Factor

Definition

NE Tolt Hill Road

NE Carnation Farm Road

NE 124th Street

NE Woodinville-Duvall Road

Most important factors

Transportation

Benefit to connectivity during flood events

Fair

Poor

Good

Good

Access

Reduction in isolation from emergency services and essential supplies

Great

Fair

Great

Good

Second most important factors

Traffic

Benefit to travel time and traffic safety during flooding

Fair

Fair

Good

Fair

Infrastructure

Amount of roads, bridges, and culverts that would need to be replaced

Good

Good

Good

Fair

Environment

Impact to wildlife, wetlands, and cultural resources.

Good

Fair

Good

Good

Third most important factors

Hydraulics

Ability to meet flood regulations

Fair

Poor

Fair

Poor

Geotechnical

Soil conditions

Poor

Good

Poor

Fair

Geomorphic

Risk of river movement and erosion

Good

Fair

Good

Good

Land Use

Impact to agricultural land, open space land, and shorelines.

Good

Good

Great

Great

Real Property

Cost and complexity to purchase additional public right-of-way

Fair

Fair

Poor

Fair

Fourth most important factors

Constructability

Cost and complexity of construction

Good

Good

Fair

Poor

Stormwater

Cost to manage stormwater runoff

Good

Fair

Good

Good

Fifth most important factor

Utility Impact

Complexity of moving existing utilities.

Fair

Fair

Good

Fair

 

Project phases and timeline

Phase one: feasibility study (December 2022 to October 2024)

  • The team analyzed the four major roadways that cross the Snoqualmie Valley to learn which two roadways are most practical and likely to succeed. This phase identified NE Tolt Hill Road and NE 124th Street as the best roadways to move forward to phase two of the study.

Phase two: alternative analysis (April 2025 to June 2027)

  • The team will compare the two recommended options from phase one to help reduce the impacts to traffic movement during times of flood.
  • In this phase, the project team will share what they learned in phase one with other government agencies.
  • The community will be involved and will be asked to share feedback about the options during this phase.
  • The team will select one road that will move forward to phase three.
  • Identifying funding for phase three of the project.
     

Phase three: preliminary design (dependent on funding availability)

  • This phase involves a lot of planning and checking to make sure everything will work as expected from the previous phases. The goal is to have a clear and practical design that can be used to start the design phase and better protect our roads from floods.

Project partners

Those working on the study include:

When government partners work together on a study, we can achieve much more than if we worked alone. Combining our resources, like money, knowledge, and skilled workers, allows us to do bigger and better research while being responsible stewards of public funds.

Additional benefits:

  • Each partner brings its own expertise, which helps create well-rounded and accurate results.
  • Sharing our data makes the findings more reliable.
  • Creates consistent policies and avoids conflicts.

Budget and funding sources

King County Flood Control District provided $1,300,000 to fund phase one and phase two of the Feasibility Study. Further grant funding will be needed to design and construct.

Community involvement

King County will do the following:

  • During phase two of the study, the community is being asked to provide feedback about the improvement options. A survey will be open from November 2 to 20, 2026 for the public to help the County learn more about the factors the community values in making this decision.
  • Provide updates on social media with any project milestones.
  • Send email notices. Subscribe to the Snoqualmie Cross Valley Study list to receive email or text message updates. 
  • Update this project website when opportunities for the public to get involved become available.
 

Growth of area

In the late 1800s and early 1900s, the valley was a big logging area. Early roads were just rough trails to move logs from the forests to sawmills and towns. These trails often followed rivers or ridges, making it easier for horse-drawn wagons and early trucks to get through.

Railroads were also important for the valley. By the late 1800s, Seattle, Lake Shore and Eastern Railway built a line through the valley, connecting Seattle to the timberlands. Some of today’s roads follow these old railroad routes. When the railroads weren’t needed for logging anymore, some routes became roads for local communities.

As towns like Snoqualmie, North Bend, and Fall City grew, the road system expanded. Paved highways, like State Route 202, replaced the old dirt and gravel roads, making it easier to travel to places like Seattle and Issaquah. Today, while many roads are used by commuters and tourists, the history of logging and railroads is still a big part of the valley’s character.

The Snoqualmie Valley is now home to around 56,000 people and is still known for its agricultural land and forestry. The fertile land in the valley is prone to flooding, especially from the Snoqualmie River.

Frequently asked question

Because our funding is limited, we’ve broken this work into three phases, and this adds additional time to the project. Creating options to help keep traffic moving across the valley during a major flood is complicated and needs careful study and analysis. Through the feasibility study, the team considered all the impacts of each of the four roadways, reviewing significant amounts of data, and many different considerations including soil, engineering, land use, and environmental with our internal groups and other partners in the community.  The team is working as fast as possible while being thorough and diligent. 

 

There isn’t another road where a fifth bridge could be built. The land where a fifth crossing could be built is not designated for roads or bridges. It is more cost effective to improve an existing road crossing the valley. 

 

Raising any road would be extremely expensive. The County has a very limited budget and cannot currently afford to raise any of the existing roads.

 

The roads in the Snoqualmie River Valley have a rich history. Long before cars and modern roads, Native American tribes used footpaths to travel through the valley. These paths followed natural routes along the river and through the forests. Later, as settlers arrived and the area grew, some of these footpaths were turned into roads. In other parts of the valley, railroads were built to move timber and other goods. After the railroads were no longer needed, some of the old railroad routes were converted into roads that we still use today. Many of the current roads in the Valley were built before our current road design and construction standards. 

 

At the end of phase two and after input from cities, community partners, and the community, King County will identify the preferred option. Once the preferred option is selected and if funding is secured, engineers will begin the design process. We are actively seeking state and Federal funding sources for the design.

The state and WSDOT are responsible for maintaining and improving state highways. King County is responsible for maintaining and improving roads and bridges that are located in unincorporated King County and are not state routes. All the cross-valley routes are in unincorporated King County, so the county is responsible for them.  We will continue to coordinate with the State of Washington and WSDOT and will review state funding opportunities as available.

The King County Road Services Division is in regular communication with the WSDOT NE Tolt Hill Road/SR 203 roundabout design team. If King County were to select NE Tolt Hill Road as the alternative, significant coordination would occur with WSDOT to ensure the new roundabout and the trestle road will connect. You can learn more about the planned WSDOT Roundabout here. 

Photos

Flooded road.

December 10, 2025: several atmospheric rivers caused unprecedented flooding throughout Western Washington. NE 124th Street in the Snoqualmie River Valley was closed due to water over the roadway. 

 

On December 5, 2023, a storm caused flooding in the Snoqualmie Valley on NE 80th Street. It rained heavily for several days because of an atmospheric river, which made the rivers overflow and flood the area.

  

On January 7, 2009, a rainstorm hit the Snoqualmie River Valley. Heavy rain and melting snow from December 2008 caused the Snoqualmie River near Carnation to rise to 62.31 feet Photo: King County iMap.