Performance Audit of the Georgetown Combined Sewer Overflow Project
September 9, 2014
The Wastewater Treatment Division (WTD) has some best practices in place for managing large capital projects. However, WTD selected its preferred alternative for controlling sewer overflows in the Georgetown area based on insufficient analysis of alternatives. Project costs are expected to increase substantially, and WTD lacks mechanisms to control project cost growth in early project development phases. We recommend that WTD consider alternatives to the projects identified in the Combined Sewer Overflow Control Plan, develop performance measures, and provide additional oversight to control project cost growth and minimize potentially substantial program cost and rate increases.
Recommendation Status
Of the 8 recommendations:
- DONE: 7
Recommendations have been fully implemented. Auditor will no longer monitor. - PROGRESS: 0
Recommendations are in progress or partially implemented. Auditor will continue to monitor. - OPEN: 0
Recommendations remain unresolved. Auditor will continue to monitor. - CLOSED: 1
Recommendation is no longer applicable. Auditor will no longer monitor.