Sammamish Plateau Diversion
The Sammamish Plateau Diversion Project will build new wastewater infrastructure to serve the growing East Lake Sammamish area.
Project description
The Sammamish Plateau Diversion Project will create new infrastructure to manage some wastewater flows from the East Lake Sammamish area. Currently, wastewater flows from the Sammamish Plateau travel to South Treatment Plant in Renton. When the project is finished, a portion of those flows will travel north to King County’s Brightwater Treatment Plant.
This project will add capacity to serve current and future populations in a busy, growing area.
Project update
August 21, 2024
Our team is preparing for field work in the project area this fall. During this work, the project team will be drilling along East Lake Sammamish Parkway Northeast to sample soil and install groundwater monitoring wells. This will help us better understand the conditions under the road.
This work requires temporary single-lane and turn-lane closures on East Lake Sammamish Parkway Northeast between Northeast 49th Place and Northeast Inglewood Hill Road between 9:30 a.m. and 3:30 p.m. Work hours are between 7 a.m. and 8 p.m., Monday through Friday. If you live nearby or travel through the area, you can expect minor traffic delays.
During this work, flaggers will direct travel throughout the area. The contractor will maintain local and emergency access. Flaggers will treat school buses as an emergency vehicle to reduce delays.
The City of Sammamish has approved the permit for King County’s project team to begin this work, and final schedule details are being confirmed. We expect this work to take place in September or early October for about two to three weeks, depending on field conditions. We will send listserv updates with more information when the work schedule is finalized.
Learn about the latest project update.
We welcome you to contact us at any time during the project to talk, ask questions, express concerns, and give feedback and input.
Previous project updates
- Permit approved for East Lake Sammamish Parkway single-lane closures, August 2024
- Upcoming work along East Lake Sammamish Parkway expected to begin later this summer, July 2024
- New schedule for upcoming work along East Lake Sammamish Parkway, July 2024
- East Lake Sammamish Parkway single-lane closures, July 2024
- Field Work coming up this summer on East Lake Sammamish Parkway, May 2024
- King County’s Sammamish Plateau Project looks forward to a busy year, February 2024
- Welcome to the Sammamish Plateau Diversion Project, December 2023
- King County launches the Sammamish Plateau Diversion Project, Fall 2023
Project timeline
2023 - 2025 | 2026-2028 | 2028-2030 |
---|---|---|
Alternatives Analysis | Design | Construction |
Project timelines may change due to a number of factors. The Sammamish Plateau Diversion Project is in an early phase. We will provide updates as our work progresses and any schedule changes are needed.