Skip to main content

Coal Creek Bridge No. 3035A Replacement Project

Project completed

The new Coal Creek bridge, completed in May 2023, winds over the creek below SE Lake Walker Road which leads into the Lake Walker community.

Status update

May 30, 2023

Crews finished the striping on the new Coal Creek bridge at the end of May 2023.

We thank the community for your patience during this project. Enjoy your new bridge!

See the latest construction photos.

Maps

Project area.

Coal Creek Bridge No. 3035A project location.

 

Map showing temporary road and bridge.

The old bridge was closed and traffic shifted to a temporary bridge in 2022. This configuration remained in place until the new Coal Creek bridge opened in spring 2023. Larger view JPG 185KB

24/7 Road Helpline

24/7 Road Helpline

Call us for help at 206-477-8100 or 1-800-527-6237 with road maintenance and traffic safety issues in unincorporated King County — 24 hours a day

Project overview

The old 64-year-old timber support structure was decaying, the 109-year-old steel floor beams were rusted, the paint was peeling, and the bridge had weight restrictions for heavy trucks. All traffic used a temporary bypass bridge throughout construction until spring 2023, when the new bridge opened.

Work to remove and replace the old Coal Creek Bridge on SE Lake Walker Road was originally planned for summer 2021, but was delayed one year to spring/summer 2022. The one-year delay was needed because crews are only permitted to do in-water work during late spring and summer. The new, replacement bridge, scheduled for completion in winter 2023, will carry no weight restrictions, and is expected to last for decades.

Construction timeline

  • Pre-construction utility relocation: Summer 2021
  • Construction of temporary bridge and traffic shift: Winter/early spring 2022
  • Old bridge removed and new bridge built: Spring/summer 2022 through winter 2023
  • Project complete: Winter 2023

Bridge history

  • Built in 1958 with timber creosote substructure
  • Used recycled superstructure from a different bridge
  • Is sole access bridge - serves single family and mobile homes
  • Is two-lane single span bridge, 41 feet long and 18 feet wide
  • Has 310 vehicles per day including about 5 trucks per day

Construction photos

Bridge pour.
Feb. 17, 2023 – One crew member stops traffic while others work on the curbs along the new bridge. Permanent guardrail and bridge railing are scheduled to be installed in early spring 2023. These will replace the concrete barriers and orange safety barrels along the bridge.


Bridge pour.
Feb. 7, 2023 – The new bridge stretches across Coal Creek into the Lake Walker community.


Bridge pour.
Feb. 7, 2023 – A stop sign gives drivers more time to see traffic coming over the new permanent bridge.


Bridge pour.
Dec. 14, 2022 – Our contractor crew takes advantage of the dry weather before the next snow storm to begin the new bridge deck construction.


Adding supports.
Oct. 18, 2022 – It takes several crewmembers to set a massive girder for the new Coal Creek bridge.


Adding supports.
Oct. 14, 2022 – A huge crane safely hoists a girder for the new bridge.


Adding supports.
Sept. 16, 2022: Crews continue to make progress by adding supports to the new bridge.


A crewmember forms rebars
Aug. 24, 2022: A crewmember forms rebars for the first abutment—what connects the road—to the new bridge.


Excavator at work.
Aug. 12, 2022: Crewmembers direct the pour of concrete for the new bridge.


Excavator at work.
June 30, 2022: The entire bridge is removed, an excavator is used to dig out the remaining creosote timber support beams. The large pipe down the center keeps the running stream safely away from construction activity.


Excavator at work.
June 30, 2022: With the bridge deck removed, crews use large metal claws attached to a boom to claw away the old, rusted metal side rails.


Excavator at work.
June 14, 2022: Crews finish routing the stream through a large metal pipe to keep fish and wildlife safe from construction activity. The old Coal Creek Bridge pictured here will be completely removed on June 30, 2022.


Coal Creek truck and 60s.
June 10, 2022: A large truck transports 60-inch pipes for fish bypass over the temporary bridge.


Coal Creek 60s.
June 10, 2022: A close-up look at two of the 60-inch pipes for fish bypass.


Culvert replacement.
May 24, 2022: An old, worn-out culvert is replaced to help direct the flow of water through Coal Creek.


Temporary bridge fix.
May 20, 2022: The wider approach to the temporary bridge (shown above) was added in May 2022. The wider approach helps larger vehicles like trailers and buses to cross more easily.


Stop signs.
May 20, 2022: Stop signs at both sides of the temporary bridge help increase safety for travelers coming to and from the Lake Walker community.


Existing and temporary bridge, looking west.
March 29, 2022: Travelers will now use the single-lane temporary bridge (left side of photo). Crews will return in late May or June to remove the existing bridge (right side of photo). We can only do work over and in the creek during the warmer months when there is less impact to fish.


Finishing touches to the new, temporary bridge.
March 18, 2022: Crews add the finishing touches to the new, temporary bridge (right side of photo). The existing Coal Creek bridge (left side of photo) will be closed to traffic once traffic is shifted onto the temporary bridge.


Installing bridge deck on temporary bridge.
March 10, 2022: Crews work to install the bridge deck on the temporary Coal Creek Bridge. This temporary bridge will be in place throughout construction of the new, replacement bridge.


Tractor smooths out approach ramp.
March 10, 2022: A tractor smooths out the top of the approach ramp crews use to access the bridge decking that is under construction on the temporary Coal Creek Bridge.


Coal Creek Bridge 3035A.
Coal Creek Bridge No. 3035A located southeast of Black Diamond in unincorporated King County.

 

Why King County is replacing this bridge

Losing steel.
We are losing sections of steel.

Severely rusting.
The super-structure is 109 years old and severely rusting.

Timber issues.
The 64-year-old creosote timbers are rotting.

Paint issues.
Paint peeling.

Frequently asked questions

The existing bridge is deteriorating and needs to be replaced. The 64-year-old timber support structure is decaying, the 109-year-old steel floor beams are severely rusting, the paint is peeling, and the curve in the road and bridge do not provide adequate visibility to oncoming traffic.

The bridge has been categorized as structurally deficient and functionally obsolete.

Structurally deficient means there are significant load carrying elements of the bridge that are in poor condition due to deterioration and/or damage or the waterway opening provided by the bridge is insufficient causing water overtopping with significant traffic delays. The fact that a bridge is “structurally deficient” does not imply that it is likely to collapse or that it is unsafe. It means that the bridge must be frequently monitored, inspected and maintained.

A functionally obsolete bridge is one that was built to standards that are not used today. Functionally obsolete bridges are those that do not have adequate load carrying capacity, lane widths, shoulder widths, approach roadway alignment, horizontal and vertical clearances to serve current traffic demand, or those that may be occasionally flooded.

As of September, 2021, the Roads Services Division bridge inspection team reports the existing bridge could only remain open if additional weight restrictions (more than there are today) were in place by winter 2022. For this reason, we will build a temporary bypass bridge and permanently close the old, existing bridge in winter 2022. Crews will return in spring or summer 2022 to remove the old bridge and build a permanent replacement. The temporary bypass bridge will not have any weight restriction.

The county has shifted all traffic onto the temporary bridge. The temporary bridge has one single lane, and there are no weight limit restrictions on the temporary bridge.

Noise levels will be typical for high- impact construction, including excavation, jack hammering, and saw-cutting.

Construction crews will typically work Monday through Friday during the day but there may be occasional weekend and/or nightwork.

Construction barriers will surround the construction area to contain construction-related materials from polluting the water. Also, the creek will be routed through a temporary bypass pipe to further protect fish and wildlife.

Yes.

The projected bridge replacement cost is $4.7 million.

Project documents

expand_less