Coal Creek Bridge No. 3035A Replacement Project
Project completed
The new Coal Creek bridge, completed in May 2023, winds over the creek below SE Lake Walker Road which leads into the Lake Walker community.
Status update
May 30, 2023
Crews finished the striping on the new Coal Creek bridge at the end of May 2023.
We thank the community for your patience during this project. Enjoy your new bridge!
See the latest construction photos.
Maps
Coal Creek Bridge No. 3035A project location.
The old bridge was closed and traffic shifted to a temporary bridge in 2022. This configuration remained in place until the new Coal Creek bridge opened in spring 2023. Larger view JPG 185KB
Project overview
The old 64-year-old timber support structure was decaying, the 109-year-old steel floor beams were rusted, the paint was peeling, and the bridge had weight restrictions for heavy trucks. All traffic used a temporary bypass bridge throughout construction until spring 2023, when the new bridge opened.Work to remove and replace the old Coal Creek Bridge on SE Lake Walker Road was originally planned for summer 2021, but was delayed one year to spring/summer 2022. The one-year delay was needed because crews are only permitted to do in-water work during late spring and summer. The new, replacement bridge, scheduled for completion in winter 2023, will carry no weight restrictions, and is expected to last for decades.
Construction photos
Feb. 17, 2023 – One crew member stops traffic while others work on the curbs along the new bridge. Permanent guardrail and bridge railing are scheduled to be installed in early spring 2023. These will replace the concrete barriers and orange safety barrels along the bridge.
Feb. 7, 2023 – The new bridge stretches across Coal Creek into the Lake Walker community.
Feb. 7, 2023 – A stop sign gives drivers more time to see traffic coming over the new permanent bridge.
Dec. 14, 2022 – Our contractor crew takes advantage of the dry weather before the next snow storm to begin the new bridge deck construction.
Oct. 18, 2022 – It takes several crewmembers to set a massive girder for the new Coal Creek bridge.
Oct. 14, 2022 – A huge crane safely hoists a girder for the new bridge.
Sept. 16, 2022: Crews continue to make progress by adding supports to the new bridge.
Aug. 24, 2022: A crewmember forms rebars for the first abutment—what connects the road—to the new bridge.
Aug. 12, 2022: Crewmembers direct the pour of concrete for the new bridge.
June 30, 2022: The entire bridge is removed, an excavator is used to dig out the remaining creosote timber support beams. The large pipe down the center keeps the running stream safely away from construction activity.
June 30, 2022: With the bridge deck removed, crews use large metal claws attached to a boom to claw away the old, rusted metal side rails.
June 14, 2022: Crews finish routing the stream through a large metal pipe to keep fish and wildlife safe from construction activity. The old Coal Creek Bridge pictured here will be completely removed on June 30, 2022.
June 10, 2022: A large truck transports 60-inch pipes for fish bypass over the temporary bridge.
June 10, 2022: A close-up look at two of the 60-inch pipes for fish bypass.
May 24, 2022: An old, worn-out culvert is replaced to help direct the flow of water through Coal Creek.
May 20, 2022: The wider approach to the temporary bridge (shown above) was added in May 2022. The wider approach helps larger vehicles like trailers and buses to cross more easily.
May 20, 2022: Stop signs at both sides of the temporary bridge help increase safety for travelers coming to and from the Lake Walker community.
March 29, 2022: Travelers will now use the single-lane temporary bridge (left side of photo). Crews will return in late May or June to remove the existing bridge (right side of photo). We can only do work over and in the creek during the warmer months when there is less impact to fish.
March 18, 2022: Crews add the finishing touches to the new, temporary bridge (right side of photo). The existing Coal Creek bridge (left side of photo) will be closed to traffic once traffic is shifted onto the temporary bridge.
March 10, 2022: Crews work to install the bridge deck on the temporary Coal Creek Bridge. This temporary bridge will be in place throughout construction of the new, replacement bridge.
March 10, 2022: A tractor smooths out the top of the approach ramp crews use to access the bridge decking that is under construction on the temporary Coal Creek Bridge.
Coal Creek Bridge No. 3035A located southeast of Black Diamond in unincorporated King County.
Frequently asked questions
The existing bridge is deteriorating and needs to be replaced. The 64-year-old timber support structure is decaying, the 109-year-old steel floor beams are severely rusting, the paint is peeling, and the curve in the road and bridge do not provide adequate visibility to oncoming traffic.
The bridge has been categorized as structurally deficient and functionally obsolete.
Project documents
- Virtual community meeting presentation - June 22, 2021 PDF 5MB
- Flyer - June 1, 2021 PDF 211KB
- Flyer - July 15, 2020 PDF 631KB
- Notice of Action Taken (NAT) - Issued, January 9, 2020 PDF 1MB
- Determination of Non-Significance (DNS) - Issued, December 10, 2019 PDF 1MB
- State Environmental Policy Act (SEPA) Environmental Checklist - Signed, November 22, 2019 PDF 5MB
- Coal Creek Bridge Replacement Project: Bridge Type, Size and Location report - November 16, 2019 PDF 67MB
- The Bridge Type Size and Location (TS&L) report evaluates three bridge design alternatives for the replacement of the Coal Creek Bridge. The TS&L report considered costs, environmental impacts, right-of-way acquisition, community feedback, construction phasing and staging needs and project schedule. The report is used to help King County determine a selection of the preferred final bridge design alternative to replace the Coal Creek Bridge.
- Open house materials - March 26, 2019:
- Display boards PDF 11MB
- Handout PDF 469KB
- Comments summary PDF 4MB
- Flyer - March 7, 2019 PDF 86KB