Harris Creek fish passage project
Snoqualmie-Skykomish Watershed
The Harris Creek Fish Passage Restoration – Snoqualmie Basin 2015 project is located approximately 3 miles east of the city of Duvall, north of Stillwater, at the intersection of NE Stossel Creek Way and NE 138th Place. Harris Creek is a tributary to the Snoqualmie River, entering the right bank at approximately river mile 19. The project location is approximately five miles upstream from the confluence with the Snoqualmie River.
Project location
Project purpose
This project restored fish passage to more than 4 miles of upstream habitat on Harris Creek and its tributaries. Harris Creek supports coho, steelhead/rainbow, and cutthroat trout.
Project features
The Harris Creek Fish Passage Improvement Project:
- removed a 25-foot long failed concrete fishway and
- installed a roughened channel of well graded streambed mixture and logs for approximately 95-feet.
Financial summary
Revenue | 2012 Revenue | 2013 Revenue | 2014 Revenue | 2015 Revenue | Total Revenue |
---|---|---|---|---|---|
KCD Grant | $57,000.00
|
$57,000.00 | |||
SWM | $12,000.00 | $42,000.00 | $97,350.00 | $175,000.00 | $326,350.00 |
Total Revenue | $69,000.00 | $42,000.00 | $97,350.00 | $175,000.00 | $383,350.00 |
Expenditures | Actuals through Sept 2015 | 30% Baseline | Remaining/Variance |
---|---|---|---|
Phase 1 - Planning |
$43,598.00 |
$34,125.00 |
($9,473.00) |
Phase 2 - Preliminary Design Phase |
$20,380.00 |
$28,441.00 |
$8,061.00 |
Phase 3 - Final Design Phase |
$39,656.00 |
$39,193.63 |
($462.37) |
Phase 4 - Implementation Phase |
$109,348.00 |
$267,091.76 |
$157,749.76 |
Phase 5 - Close-out Phase |
$0.00 |
$4,456.40 |
$4,456.40 |
Phase 6 - Acquisition Phase (easement) |
$18,410.00 |
$0.00 |
($18,410.00) |
Estimate at Completion |
$216,913.40 |
$373,307.79 |
$156,394.39 |
A King County Roads crew constructed the project, which significantly lowered the over-all construction cost.
Timeline
Phases | Planned Schedule | Actual Schedule | Reason for Variance |
---|---|---|---|
Start date |
Oct 2012 |
Oct 2012 |
|
30% Design |
Feb 2013 |
Dec 2014 |
workload conflicts |
Permit submittal |
Oct 2013 |
Oct 2014 |
|
Final Design |
Mar 2014 |
Mar 2015 |
|
Construction |
Jul/Aug. 2014 |
Aug. 2015 |
|
Close-out |
June 2015 |
Forecast - Jun 2016 |
|
Issues moving forward
Per WDFW and ACOE permit requirements we will monitor the vegetation establishment for 3 years to confirm 80-percent survival. Our ERES monitoring group will monitor channel and vegetation responses over the next 5-years under the adopted monitoring plan established during the design phase.
Key lessons learned and/or vexing issues that need follow up
Other than some initial design delays due to workload conflicts, this project actually went quite smoothly.
Project contacts
Please contact us with any information, comments, or concerns you may have regarding the project:
Carolyn Butchart, P.E.
Ecological Restoration and Engineering Services
King County Water and Land Resources Division
201 S. Jackson Street, Suite 600
Seattle, WA 98104-3855
carolyn.butchart@kingcounty.gov
Office: 206-477-4659
Cell: 206-496-8637
Mary Maier
Snoqualmie Basin Steward
mary.maier@kingcounty.gov
206-477-4762
Project documents
The Harris Creek Fish Passage Project documents are available in Adobe Acrobat format. For help using Acrobat files, please visit our Acrobat help page.
- Harris Creek Fish Passage Project Monitoring Report for Years 1 & 2: 2016 - 2017 (2 MB)
- Harris Creek Fish Passage Project 90% plans (6 MB)
- Harris Creek Restoration Plan Drawing (809 KB)
- Harris Creek Restoration Cross Section (927 KB)
For more information about the Harris Creek Fish Passage Project, please contact Carolyn Butchart, engineer, King County Ecological Restoration and Engineering Services or Mary Maier, Snoqualmie Basin Steward, Watershed Stewardship Unit.